The National Council of Provinces (NCOP) recently held a debate on the report of the 2026 Provincial Week, which took place in August. The report follows oversight visits conducted by NCOP permanent delegates across the nine provinces from 17 to 21 August 2026 to assess service delivery, with a particular focus on incomplete, delayed and abandoned infrastructure projects.
This year’s Provincial Week was held under the themes: “Confronting the challenges facing the timely delivery of viable public infrastructure to communities” and “Building viable municipalities for the enhanced delivery of basic services”.
Tabling the report to open the debate, NCOP Deputy Chairperson Mr Les Govender said the theme was well-chosen and spoke directly to the lived realities of citizens. “This theme challenges us to confront those challenges head-on, not to run away from them, not to hide them in reports, but to confront them, name them, and demand solutions.
“Our mandate was clear: to assess progress in the implementation of government-funded infrastructure projects and initiatives aimed at improving basic service delivery, municipal viability, accountability, and public participation,” he said.
Highlighting the findings of the Provincial Week, the Deputy Chairperson noted that a key challenge across many provinces was the widening gap between the delivery of new infrastructure and the sustainable operation and maintenance of existing assets. He pointed out that completed projects face serious sustainability challenges due to inadequate funding, a lack of maintenance, operational backlogs, and widespread water shortages, aging networks, and unreliable services in districts across South Africa.
“This is not an abstract problem; it is a daily reality for millions of people. In districts such as OR Tambo and Chris Hani in the Eastern Cape, and Mopani in Limpopo, communities told us the same painful story: taps run dry for days and weeks, aging pipes burst and leak, water tankers fail to arrive, and infrastructure that has been completed remains non-functional,” said Mr Govender.
Provincial Week also uncovered significant sanitation and wastewater compliance challenges. Many wastewater treatment plants are operating below regulatory requirements, failing to comply with Green Drop standards, and discharging poorly treated or untreated sewage into rivers and streams, risking severe environmental and health outcomes. The report further noted weak performance monitoring, finding that in some municipalities contractors were appointed and paid, yet they abandoned sites with no consequences or tracking of performance.
The NCOP outlined a long list of recommendations for municipalities and provincial governments to address these challenges, including strengthening technical and institutional capacity.
The Deputy Chairperson emphasised the need to build the capacity of municipalities and departments to plan, deliver, and manage infrastructure effectively. “We need to improve the recruitment and retention of engineers, technicians, project managers, and financial managers. We must also reduce our overreliance on consultants and ensure that where consultants are used, skills transfer is mandatory,” he said.
The NCOP also recommended that every municipality allocate specific funding for maintenance, develop costed maintenance programmes, and ensure no new projects are approved without a funded maintenance plan. “Commitments made during Provincial Week must be implemented. Where there is corruption and misuse of funds, there must be consequences. Oversight without consequences is just a visit,” Mr Govender stressed.
Participating in the debate, ANC MP and Chairperson of the Select Committee on Cooperative Governance and Traditional Affairs Mr Mxolisi Kaunda said the success of oversight should not be measured by the number of meetings or site visits, but by whether it accelerates service delivery and improves lives.
“Effective oversight must follow a project beyond its announcement, budget allocation and sod-turning ceremony. We must establish whether planning is complete, funds are spent for their intended purpose, construction meets required standards and communities are receiving services. Accountability is not complete when Parliament asks a question; it is complete when corrective action is taken and people can see the difference,” said Mr Kaunda.
Debating on behalf of the Democratic Alliance, Dr Igor Scheurkogel warned that Parliament was treating oversight the way municipalities treat Integrated Development Plans (IDPs); in other words: ticking a box, taking a picture and leaving communities waiting. “Why visit another project when communities we visited in 2024 are still waiting for promises to become services? Bringing Parliament to the people must mean bringing accountability with us,” he said.
Dr Scheurkogel also emphasised the importance of prioritising maintenance funding before infrastructure collapses, alongside better planning by local authorities.
Patriotic Alliance delegate Mr Bino Farmer noted that while Provincial Week is an important NCOP oversight mechanism, its true value must be measured by whether findings and recommendations result in meaningful corrective action. “Delays, abandoned projects, deteriorating infrastructure and municipal financial difficulties raise serious questions about planning, project management, institutional capacity and accountability. Accountability cannot remain a recommendation in a parliamentary report; it must become an operational reality,” said Mr Farmer.
Mr Edward Nzimande of the uMkhonto weSizwe (MK) Party echoed concerns regarding poor planning and a lack of infrastructure maintenance in municipalities. “Government performance must be measured by its impact on the socio-economic issues affecting citizens. There is no amount of parliamentary oversight that can cure poor planning, as oversight comes as an after-effect. Recommendations must produce action.
“People cannot drink an undertaking, they cannot travel on a progress report, and they cannot raise children safely beside an overflowing sewer while the government explains another revised completion date,” Mr Nzimande said.
Deputy Minister of Cooperative Governance and Traditional Affairs Prince Zolile Burns-Ncamashe agreed with the NCOP’s recommendations, underscoring the importance of ensuring that infrastructure is properly planned, fully operational, and adequately maintained. “The findings arising from Provincial Week reinforce a central principle: infrastructure must be planned and managed as an integrated system, not as a collection of disconnected projects.
“Delays in project preparation, procurement, contract management, bulk service provision, and the appointment of capable professionals often translate directly into delayed services,” he said.
The Deputy Minister pledged that government would strengthen the entire infrastructure delivery chain from planning and budgeting to implementation, operation, and maintenance. “We commit to working with municipalities, provinces, the National Treasury, the Municipal Infrastructure Support Agent, the South African Local Government Association, and other relevant departments to strengthen municipal performance, accelerate infrastructure delivery, and ensure that Provincial Week recommendations inform our oversight and support,” he promised.
Provincial Week is a high-impact oversight programme designed to assess the delivery of basic services to communities. It gives permanent delegates to the NCOP an opportunity to return to their respective provinces to assess progress and help address grassroots challenges.
Sakhile Mokoena
18 November 2026