Parliament’s Portfolio Committee on Electricity and Energy has warned that the planned decommissioning of Eskom’s coal-fired power stations in Mpumalanga must take place strictly within the Just Energy Transition (JET) framework, backed by concrete programmes to protect affected workers and surrounding communities.

The call follows recent oversight visits to three Mpumalanga power stations – Komati, Hendrina and Arnot – earmarked for decommissioning, repowering and repurposing. During the engagements, committee members heard widespread anxiety from workers over job security and from local residents who fear severe socio-economic losses as coal operations wind down.

At Komati Power Station, which ceased coal-fired generation in 2022 as part of South Africa’s shift toward cleaner energy, the committee met with Eskom management, organised labour and the Komati Steering Committee, which represents local communities.

Committee members expressed concern over the slow pace of progress since their previous oversight visit last year, questioning whether the plant’s shutdown was rushed without an adequate transition plan in place.

Komati Steering Committee representative Mr George Mpe told MPs that the closure of the power station and a nearby coal mine had devastated the local economy and stripped residents of essential services previously provided by the two entities, including a local clinic, ambulance services and sporting facilities. “These communities depended on the existence of the power station and the mine. When you remove these two entities, how do you expect us to continue surviving?” Mr Mpe asked.

Eskom management acknowledged the shortcomings, conceding that Komati was not an ideal model for executing a just transition, but maintained that lessons learned from the site would guide future closures.

Committee Chairperson Zamakhanyase Khanyase described Komati as a critical case study for South Africa’s energy transition, noting that Parliament would continue monitoring the project to ensure targets are met. “The transition from coal-based electricity to more sustainable energy sources is an important part of changing global energy systems.”

Parliament is concerned about how this transition is managed, who benefits from it, and what happens to the workers and communities whose livelihoods depended solely on coal, Ms Khanyase said.

Similar concerns emerged during visits to Hendrina and Arnot power stations, both scheduled for decommissioning, repowering and repurposing by 2030. Workers told MPs they feared their skills would become obsolete and argued that Eskom had failed to conduct meaningful consultations.

National Union of Mineworkers (NUM) full-time shop steward in Mpumalanga Mr Bobo Thani urged the committee to intervene and halt further closures until Komati’s repurposing and reskilling projects are fully operational. “The fear has been worsened by what happened at Komati, where some workers lost their jobs following the shutting down of that station,” Mr Thani said.

“Our plea is for the committee to ask Eskom to delay the planned decommissioning of Hendrina and Arnot until the full implementation of repurposing, repowering, and reskilling at Komati.”

Station management acknowledged worker anxiety over the uncertainty surrounding 2030, explaining that formal reskilling programmes cannot begin until there is clarity on which new technologies will be deployed at the sites.

However, committee members questioned Eskom’s preparedness, noting that with the 2030 deadline roughly four years away, formal reskilling initiatives have yet to start. Ms Khanyase said the committee would escalate these concerns directly to Eskom’s executive management, the Ministry of Electricity and Energy and the Presidential Climate Commission (PCC).

As part of the same oversight programme, the committee visited Kusile Power Station to assess Eskom’s compliance with an August 2026 Supreme Court of Appeal (SCA) judgment ordering the utility and state regulators to address ongoing water pollution and environmental non-compliance at the plant.

Station management briefed MPs on a revised water management action plan that reviews pollution sources, incorporates audit findings, strengthens water quality monitoring and introduces corrective measures to protect downstream water resources.

“We welcome compliance with the court orders, which was our primary focus during today’s visit. The filing of the action plans is encouraging progress, however, we should not find ourselves in this position again, where positive work is overshadowed by matters of this nature. We should not wait for court intervention, as that creates an impression of reluctance to act voluntarily,” the Chairperson said.

The committee also received a briefing from the National Transmission Company South Africa (NTCSA) on its Transmission Development Plan, in line with Parliament’s Oversight Priority Plan on infrastructure development.

Ms Khanyase stressed that expanding the national grid must support South Africa’s evolving energy mix and broader industrialisation goals, including domestic manufacturing, skills transfer, and local business participation. She warned that delays in rolling out transmission infrastructure risk constraining economic growth, deterring investment and bottlenecking new generation capacity.

Sakhile Mokoena
27 November 2026